Api Power Company Limited will be the next private
hydropower company to float its public share. It is constructing an 8.5 MW project in Darchula district. Here is my
sincere opinion regarding the Company, its projects, its future plans and
projected share price when listed in Nepal Stock Exchange.
1)
MANAGEMENT
The Company is led by Mr. Guru
Prasad Neupane. Mr. Neupane and his group have already constructed three
projects in Nepal that are in operational stage.
Name
|
Designation
|
Guru Prasad Neupane
|
Chairman
|
Sanjeev Neupane
|
Managing Director
|
Mahendra Neupane
|
Director
|
Satish Neupane
|
Director
|
2) CAPITAL STRUCTURE
The authorized, issued and paid up
capital are NPR 1.2 billion, NPR 1 billion and NPR 700 million respectively
Breakdown of issued capital
Details
|
Amount
|
Percentage
|
Status
|
Promoters
|
NPR. 600 million
|
60%
|
paid
|
Local People
|
NPR. 100 million
|
10%
|
paid
|
General Public
|
NPR. 300 million
|
30%
|
due
|
Total
|
NPR
1 billion
|
100%
|
3)
NAUGARH GAD SMALL HYDROELECTRIC PROJECT (8.5W)
It is a flagship project of the
Company. It lies in Naugarh Gad River, a tributary of Chameliya River, in
Darchula and Baitadi districts. The river originates from the Api Himalayan
Range.
The project is conceived as a run-of-river project with 155 meter gross head and a design discharge of 7.46 m3/sec.
The major structures of the project
consists of 30 meter weir, twin settling basin, 4,500 m long penstock pipe,
31mx14.5mx13m (LxBxH) power house with 2 Francis turbine, 30m long tailrace
canal and 5 km transmission line.
3.1)
Technical aspect of the project
a) Hydrology and Power:- It is a snow-fed river. The contract energy is 51,934,939
kWh which makes 70% net plant factor. This is considered to be very good. In
addition, 21% will be dry energy which is also a plus point of this project.
b) Geography:- The geography of the project is very favorable.
Particularly, the penstock alignment area lies in the flat land making easier
for construction. The risk of landslide and other geographical risks are
minimal.
c) Electro-Mechanical Equipments:- The Company has used Adritz's electro-mechanical equipments. Adritz is a highly reputed Austrian company. Unlike other Chinese knock-offs, I believe this project will not suffer from penalty in the years to come due to machinery breakdown.
d) Transmission line:- The risk of power evacuation is nil for this
project. The power will be evacuated through a 132 kV transmission line at Balanch Substation which is 5
km away from the powerhouse. 5 km is considered to be shorter for a size of 8.5
MW. Additionally, there is another alternative of a 33 kV transmission line for power evacuation. This can be used if there is any delay in 132 kV transmission line.
3.2)
Local Problems
It is situated in Far Western
Development Region of Nepal where total population is relatively small. Apart
from this, hydropower project is not a new thing in this region. NEA’s 30 MW
Chameliya project is just few kilometers away. So I believe local issue will be
less and manageable. This will ensure smooth operation of the project.
3.3)
Project Status
The project is almost completed.
Test operation is scheduled to be conducted at the end of Baishak 2072.
3.4)
Project Cost
The cost per MW is about NPR. 155
million. This is one of the lowest costs I have seen in the recent time. Mr.
Neupane and his team have done a commendable job.
3.5)
Tariff
The main downfall of this project is
its PPA rate. It is not the new tariff. Its PPA rate is as follows.
Year
|
Dry
energy rate per kWh
|
Wet
energy rate per kWh
|
Commercial Operation Date (COD)
|
7.00
|
4.00
|
II Year
|
7.21
|
4.12
|
III Year
|
7.42
|
4.24
|
IV Year
|
7.63
|
4.36
|
V Year
|
7.84
|
4.48
|
VI Year
|
8.05
|
4.6
|
VII Year
|
8.26
|
4.72
|
VIII Year
|
8.47
|
4.84
|
IX Year
|
8.68
|
4.96
|
X Year
|
8.89
|
5.08
|
From 10th year, the tariff will
remain constant for the entire PPA period.
4)
FUTURE PROJECTS OF THE COMPANY
The Company plans to construct an 8
MW Upper Naugarh Gad Small Hydropower Project that lies in upstream of existing
project. Application for PPA has been made already.
Similarly, it is planning to
invest NPR. 150 million in Arun Kabeli Power Limited, a company owned by Mr.
Guru Prasad Neupane. Construction of 25 MW Kabeli B-1 Hydropower Project that
belongs to Arun Kabeli Power limited has just started. The construction period
is expected to be three years.
5)
FINANCIALS
Actual
|
|||||
Detail/Fiscal Year
|
2068/69
|
2069/70
|
2070/71
|
||
Share Capital
|
10,213,000
|
82,748,000
|
502,150,000
|
||
Long-term Loan
|
-
|
2,394,000
|
173,435,000
|
||
Investment
|
-
|
-
|
90,100,000
|
||
Income from Energy
Sale
|
-
|
-
|
-
|
||
Government subsidy
|
|||||
Income from Investment
|
|||||
Profit/(loss)
|
323,000
|
2,185,000
|
3,727,000
|
||
EPS
|
3.16
|
2.61
|
0.74
|
||
Book Net worth
|
89.34
|
96.08
|
98.61
|
||
Projected
|
|||||
Detail/Fiscal Year
|
2071/72
|
2072/73
|
2073/74
|
2073/74
|
2074/75
|
Share Capital
|
1,000,000,000
|
1,000,000,000
|
1,000,000,000
|
1,000,000,000
|
1,000,000,000
|
Long-term Loan
|
970,693,000
|
960,558,000
|
1,799,222,000
|
1,705,202,000
|
1,600,210,000
|
Investment
|
150,000,000
|
150,000,000
|
150,000,000
|
150,000,000
|
150,000,000
|
Income from Energy
Sale
|
55,308,000
|
241,870,000
|
292,317,000
|
572,396,000
|
589,047,000
|
Government subsidy
|
46,750,000
|
-
|
40,000,000
|
-
|
-
|
Income from Investment
|
4,135,000
|
6,540,000
|
1,740,000
|
16,740,000
|
16,740,000
|
Profit/(loss)
|
58,345,000
|
59,108,000
|
108,706,000
|
246,939,000
|
273,332,000
|
EPS
|
5.83
|
5.91
|
10.87
|
24.69
|
27.33
|
Book Net worth
|
100.14
|
101.05
|
101.92
|
106.61
|
111.95
|
*NPR 5 million per MW as a government subsidy is included in the calculation.
By looking at the financials, the
Company's projection doesn’t look lucrative for the first few years of
operation. All the indicators are below average. The low EPS is due to
over-capitalization.
Apart from 8.5 MW project which is
almost in a verge of operation, the income from 8 MW Upper Naugarh Gad
Small Hydropower Project and 25 MW Kabeli B-1 Hydropower Project are just
a mere forecast.
If everything goes as per the plan, income from the entire NPR 1 billion investment will start arriving in the full swing after four years from the date of IPO.
6)
IPO
NIBL Capital Markets limited is the
issue manager. NPR 100 million has been raised already from the project
affected area, a mandatory rule imposed by the Government of Nepal.
The general issue of NPR 300 million
will take place in about one month from now. The final approval from SEBON is
yet to be received.
The collected amount will be utilized
to construct an eight megawatt Upper Naugarh Gad Small Hydropower Project.
7)
ICRA RATING
ICRA Nepal Limited (ICRA Nepal), the
first Credit Rating Agency in Nepal, is a subsidiary of ICRA Limited (ICRA) of
India.
ICRA Nepal has assigned “IPO Grade
3”, indicating average fundamental, to the proposed initial public offering
(IPO) of Api Power Company Limited. ICRA Nepal assigns IPO grading on a scale
of IPO Grade 1 through IPO Grade 5, with Grade 1 indicating strong fundamentals
and Grade 5 indicating poor fundamentals.
8)
VERDICT
I was confident that this 8.5 MW
would get new PPA rates but it looks like it is not going to be the case.
Previously, government had assured to revise the tariff. The condition for such
revision was to finish the construction by the end of Chaitra 2071. Now, the
deadline has crossed. This is a huge blow by the way.
Confusingly, the Company is raising
more capital than it actually needs. It looks like the craze in hydropower IPO
is well understood by the Company and it is trying to cash-in the trend.
"You never know how market
behaves tomorrow, so let’s collect capital as much as we can while market
is behaving positively" I guess this is the strategy.
I do not think it is a blunder
mistake at all. After all, our country lacks capital and whenever there
is an opportunity to collect capital then, why not?
But this will directly affect the
earning ratio. Hydropower revenue is pre-determined and fixed beforehand. Over capitalization
means more hungry mouths to feed from its fixed income.
Finally, predicting share price is
tricky in this case. It will largely depend upon the execution of future
projects. However, it is safe to say that the initial price will stay in
between NPR 200 to 300 i.e. 5.83x40 (EPSxPE ratio).
There will be an increasing trend in
share price if everything goes according to the plan. Assuming that the future projects
will be timely constructed and the capital market remains ideal, I will not be
surprised if the share price jumps above NPR 800, i.e. 24.89x40 (EPSxPE ratio)
in four years time. However, it all depends on how and when the future projects will be executed. Only time will tell. We all have to wait and see.
IPO of Barun Hydropower Company Limited
Ridi Hydropower Development Company Limited and its share price speculation.
Upper Tamakoshi Hydropower Project and Its IPO; Fully Explained
It is big and it is coming: HIDCL’s IPO
United Modi Hydropower Limited: IPO analysis.
IPO of Ngadi Group Power Limited
The project was planning to come into operation this fiscal year when i wrote the above blogpost. But now its not gonna happen. Please be informed that there will be no revenue this year.
ReplyDeletewhy is that ??
DeleteThanks Dude.....Your Analysis is credible and inclusive of analytical insights,,,
ReplyDeleteThanks sir for Your Valuable time and Making us informed about the Project...We wud like to Hear some more in future....
ReplyDeleteWHERE ARE THE FORMS AVAILABLE TO APPLY FOR THE SHARES ???
ReplyDeleteas its operation date changed, how will it effect on its share price and return.. on future..
ReplyDelete