Sunday, 27 July 2014

The next upcoming IPO: Api Power Company Limited.

Api Power Company Limited will be the next private hydropower company to float its public share. It is constructing an 8.5 MW project in Darchula district. Here is my sincere opinion regarding the Company, its projects, its future plans and projected share price when listed in Nepal Stock Exchange.



Last Update:- 4/19/2015



1) MANAGEMENT 
The Company is led by Mr. Guru Prasad Neupane. Mr. Neupane and his group have already constructed three projects in Nepal that are in operational stage.

Name
Designation
Guru Prasad Neupane
Chairman
Sanjeev Neupane
Managing Director
Mahendra Neupane
Director
Satish Neupane
Director

2) CAPITAL STRUCTURE 
The authorized, issued and paid up capital are NPR 1.2 billion, NPR 1 billion and NPR 700 million respectively

Breakdown of issued capital

Details
Amount
Percentage
Status
Promoters
NPR. 600 million
60%
paid
Local People
NPR. 100 million
10%
paid
General Public
NPR. 300 million
30%
due
Total
NPR 1 billion
100%


3) NAUGARH GAD SMALL HYDROELECTRIC PROJECT (8.5W)
It is a flagship project of the Company. It lies in Naugarh Gad River, a tributary of Chameliya River, in Darchula and Baitadi districts. The river originates from the Api Himalayan Range. 

The project is conceived as a run-of-river project with 155 meter gross head and a design discharge of 7.46 m3/sec.

The major structures of the project consists of 30 meter weir, twin settling basin, 4,500 m long penstock pipe, 31mx14.5mx13m (LxBxH) power house with 2 Francis turbine, 30m long tailrace canal and 5 km transmission line.

3.1) Technical aspect of the project
a) Hydrology and Power:- It is a snow-fed river. The contract energy is 51,934,939 kWh which makes 70% net plant factor. This is considered to be very good. In addition, 21% will be dry energy which is also a plus point of this project.

b) Geography:- The geography of the project is very favorable. Particularly, the penstock alignment area lies in the flat land making easier for construction. The risk of landslide and other geographical risks are minimal.

c) Electro-Mechanical Equipments:- The Company has used Adritz's electro-mechanical equipments. Adritz is a highly reputed Austrian company. Unlike other Chinese knock-offs, I believe this project will not suffer from penalty in the years to come due to machinery breakdown.

d) Transmission line:- The risk of power evacuation is nil for this project. The power will be evacuated through a 132 kV transmission line at Balanch Substation which is 5 km away from the powerhouse. 5 km is considered to be shorter for a size of 8.5 MW. Additionally, there is another alternative of a 33 kV transmission line for power evacuation. This can be used if there is any delay in 132 kV transmission line.

3.2) Local Problems
It is situated in Far Western Development Region of Nepal where total population is relatively small. Apart from this, hydropower project is not a new thing in this region. NEA’s 30 MW Chameliya project is just few kilometers away. So I believe local issue will be less and manageable. This will ensure smooth operation of the project.

3.3) Project Status
The project is almost completed. Test operation is scheduled to be conducted at the end of Baishak 2072. 


3.4) Project Cost
The cost per MW is about NPR. 155 million. This is one of the lowest costs I have seen in the recent time. Mr. Neupane and his team have done a commendable job.

3.5) Tariff 
The main downfall of this project is its PPA rate. It is not the new tariff. Its PPA rate is as follows.
Year
Dry energy rate per kWh 
Wet energy rate per kWh 
Commercial Operation Date (COD)
7.00
4.00
II Year
7.21
4.12
III Year
7.42
4.24
IV Year
7.63
4.36
V Year
7.84
4.48
VI Year
8.05
4.6
VII Year
8.26
4.72
VIII Year
8.47
4.84
IX Year
8.68
4.96
X Year
8.89
5.08
 From 10th year, the tariff will remain constant for the entire PPA period.

4) FUTURE PROJECTS OF THE COMPANY
The Company plans to construct an 8 MW Upper Naugarh Gad Small Hydropower Project that lies in upstream of existing project. Application for PPA has been made already.

 Similarly, it is planning to invest NPR. 150 million in Arun Kabeli Power Limited, a company owned by Mr. Guru Prasad Neupane. Construction of 25 MW Kabeli B-1 Hydropower Project that belongs to Arun Kabeli Power limited has just started. The construction period is expected to be three years.

5) FINANCIALS


Actual


Detail/Fiscal Year
2068/69
2069/70
2070/71


Share Capital
            10,213,000
         82,748,000
         502,150,000


Long-term Loan
                             -  
           2,394,000
         173,435,000


Investment
                             -  
                           -  
           90,100,000


Income from Energy Sale
                             -  
                           -  
                             -  


Government subsidy





Income from Investment





Profit/(loss)
                  323,000
           2,185,000
              3,727,000


EPS
                         3.16
                      2.61
                        0.74


Book Net worth
                      89.34
                    96.08
                      98.61









Projected


Detail/Fiscal Year
2071/72
2072/73
2073/74
2073/74
2074/75
Share Capital
      1,000,000,000
   1,000,000,000
     1,000,000,000
         1,000,000,000
         1,000,000,000
Long-term Loan
         970,693,000
       960,558,000
     1,799,222,000
         1,705,202,000
         1,600,210,000
Investment
         150,000,000
       150,000,000
         150,000,000
             150,000,000
             150,000,000
Income from Energy Sale
            55,308,000
       241,870,000
         292,317,000
             572,396,000
             589,047,000
Government subsidy
            46,750,000
                           -  
           40,000,000
                                 -  
                                 -  
Income from Investment
              4,135,000
           6,540,000
              1,740,000
               16,740,000
               16,740,000
Profit/(loss)
            58,345,000
         59,108,000
         108,706,000
             246,939,000
             273,332,000
EPS
                         5.83
                      5.91
                      10.87
                          24.69
                          27.33
Book Net worth
                    100.14
                 101.05
                    101.92
                       106.61
                       111.95
 *NPR 5 million per MW as a government subsidy is included in the calculation.

By looking at the financials, the Company's projection doesn’t look lucrative for the first few years of operation. All the indicators are below average. The low EPS is due to over-capitalization. 

Apart from 8.5 MW project which is almost in a verge of operation, the income from 8 MW Upper Naugarh Gad Small Hydropower Project and 25 MW Kabeli B-1 Hydropower Project are just a mere forecast. 

If everything goes as per the plan, income from the entire NPR 1 billion investment will start arriving in the full swing after four years from the date of IPO.

6) IPO
NIBL Capital Markets limited is the issue manager. NPR 100 million has been raised already from the project affected area, a mandatory rule imposed by the Government of Nepal.


The general issue of NPR 300 million will take place in about one month from now. The final approval from SEBON is yet to be received.

The collected amount will be utilized to construct an eight megawatt Upper Naugarh Gad Small Hydropower Project.

7) ICRA RATING
ICRA Nepal Limited (ICRA Nepal), the first Credit Rating Agency in Nepal, is a subsidiary of ICRA Limited (ICRA) of India. 

ICRA Nepal has assigned “IPO Grade 3”, indicating average fundamental, to the proposed initial public offering (IPO) of Api Power Company Limited. ICRA Nepal assigns IPO grading on a scale of IPO Grade 1 through IPO Grade 5, with Grade 1 indicating strong fundamentals and Grade 5 indicating poor fundamentals.

8) VERDICT
I was confident that this 8.5 MW would get new PPA rates but it looks like it is not going to be the case. Previously, government had assured to revise the tariff. The condition for such revision was to finish the construction by the end of Chaitra 2071. Now, the deadline has crossed. This is a huge blow by the way.

Confusingly, the Company is raising more capital than it actually needs. It looks like the craze in hydropower IPO is well understood by the Company and it is trying to cash-in the trend.

"You never know how market behaves tomorrow, so let’s collect capital as much as we can while market is behaving positively" I guess this is the strategy. 

I do not think it is a blunder mistake at all.  After all, our country lacks capital and whenever there is an opportunity to collect capital then, why not?

But this will directly affect the earning ratio. Hydropower revenue is pre-determined and fixed beforehand. Over capitalization means more hungry mouths to feed from its fixed income.

Finally, predicting share price is tricky in this case. It will largely depend upon the execution of future projects. However, it is safe to say that the initial price will stay in between NPR 200 to 300 i.e. 5.83x40 (EPSxPE ratio). 

There will be an increasing trend in share price if everything goes according to the plan. Assuming that the future projects will be timely constructed and the capital market remains ideal, I will not be surprised if the share price jumps above NPR 800, i.e. 24.89x40 (EPSxPE ratio) in four years time. However, it all depends on how and when the future projects will be executed. Only time will tell. We all have to wait and see.


SEE SIMILAR IPO REVIEW BY CLICKING THE FOLLOWING LINKS

IPO of Barun Hydropower Company Limited

Ridi Hydropower Development Company Limited and its share price speculation.

Upper Tamakoshi Hydropower Project and Its IPO; Fully Explained

It is big and it is coming: HIDCL’s IPO

United Modi Hydropower Limited: IPO analysis.

IPO of Ngadi Group Power Limited  

6 comments:

  1. The project was planning to come into operation this fiscal year when i wrote the above blogpost. But now its not gonna happen. Please be informed that there will be no revenue this year.

    ReplyDelete
  2. Thanks Dude.....Your Analysis is credible and inclusive of analytical insights,,,

    ReplyDelete
  3. Thanks sir for Your Valuable time and Making us informed about the Project...We wud like to Hear some more in future....

    ReplyDelete
  4. WHERE ARE THE FORMS AVAILABLE TO APPLY FOR THE SHARES ???

    ReplyDelete
  5. as its operation date changed, how will it effect on its share price and return.. on future..

    ReplyDelete