I
have been closely following the energy generation trend of recently completed
projects, and I must say it is pretty disappointing. Following are the projects
with their design PLF and their actual (PLF) generation.
S.N.
|
Project
|
Design PLF
|
Actual PLF
|
1
|
Ankhu Khola (8.4 MW)
|
63%
|
47% to 55% in the last
two years.
|
2
|
Radhi Hydropower (4
MW)
|
68%
|
Around 57% in the last
two years.
|
3
|
Lower Modi -1 (10 MW)
|
70%
|
Around 57% in the last
two years.
|
4
|
Charnawati Hydro (3.52
MW)
|
66%
|
Around 55% in the last
two years.
|
5
|
Siuri Khola (4.95 MW)
|
74%
|
Around 59% in the last
two years.
|
PLF
(Plant load factor) is the percentage of energy generation against its full
capacity. To calculate it, take the total amount of energy the plant produced
during a period of time and divide by the amount of energy the plant would have
produced at full capacity. Higher PLF is always better as it ensures higher
energy production leading to higher revenue.
Unfortunately,
no hydropower project (recently completed) has been able to operate at its designed
PLF. Not only this triggers the revenue loss but also may end up in paying
penalty to NEA.
What
may be the causes for such variation?
1)
First of all, we do not have mature data. Except the major rivers, none of our
rivers/rivulets are gauged. In such case, prediction of hydrology becomes a
guess work only. Reference of rainfall analysis in the similar catchment areas
becomes the main tool for forecasting the river flow.
Some
developers establish their own gauging station to measure the actual discharge,
but 1 or 2 year data is simply not enough to do the prediction.
2)
Developers are obsessed with MWs. I have seen many developers going for higher MWs
only without considering the energy generation/energy revenue aspect compared
to its installed capacity. Project optimization is completely neglected. NEA buys energy from the project that is
designed at Q40% (up to). Hence, manipulation of hydrological data becomes quite obvious.
3)
8 months is considered as wet season while the remaining 4 months is termed as
dry season. However, NEA requires at least 15 percent of the total contract
energy as dry energy. So developers may have manipulated on purpose to meet
this requirement.
4)
One of the causes is the water seepage, and it happens due to low
quality design/construction of structures.
As you have explained yourself 100% PLF is not possible due to the dry season. I agree that developers temper with the hydrology of the river to get higher MW but it is a loss to the developer themselves rather than NEA or the general people. And lastly I don't agree with your perception that water seepage due low quality design/construction of structures is an issue for lower PLF, I have seen many hydropower projects with good design and construction in Nepal.
ReplyDelete