KATHMANDU,
SEP 29 - A consortium of eight commercial banks and Hydroelectric Investment
and Development Company Ltd (HIDCL) has pledged loans amounting to Rs 3.07
billion to develop the 23.5 MW Solu Hydroelectric Project.
The
consortium led by Laxmi Bank and the project’s developer Upper Solu
Hydroelectric Company (USHEC) signed a loan facility agreement on Sunday.
USHEC
is an undertaking of ICTC Energy promoted by the ICTC Group. ICTC Group managing
Director Prabin Shrestha and representatives of the banks and HIDCL signed the
pact on behalf of their respective institutions.
The
estimated cost of the project is Rs 4.1 billion. As per the agreement, the
lenders will be investing 75 percent of the project cost and its promoters will
put up the rest. The promoters the ICTC Group holds an 80 percent stake in the
project and Blue Energy owns the rest.
Shashi
Sagar Rajbhandari, chief executive officer of USHEC, said that the loan
facility agreement was signed to conclude the financial closure for financing
the project. The project is the first among the so-called super six projects to
conclude the financial closure, and it is at an advanced stage of development
compared to the rest, said USHEC. The project’s basic infrastructure is being
built, and the construction of the main structure is scheduled to start at the
beginning of 2015.
In
2009, the Department of Electricity Development had initiated the process of
awarding eight projects varying in capacity from 5 MW to 40 MW, including the
Solu Hydroelectric Project, to private developers through competitive bidding.
After an evaluation of the bids, licences for six projects were awarded to six
different developers, including this one to the ICTC Group. On November 10,
2013, USHEC and the Nepal Electricity Authority (NEA) signed a Power Purchase
Agreement.
According
to Rajbhandari, USHEC plans to hire a contractor by the end of 2014 and begin
construction in 2015. “As per the detailed project report, we aim to complete
the construction of the project by July 2018,” said Rajbhandari, adding that
the project was slated to begin commercial operation by July 17, 2018. As for
the transmission line, Rajbhandari said the NEA would appoint a consultant and
then invite tenders in October for its construction. “The NEA has assured us
that the construction of the transmission line will be completed within April
2018,” Rajbhandari said.
The
NEA will build a 90-km-long of the transmission line while the project will
erect a 3 km section to feed the power generated by the project into the
national grid.
Source:-
e-Kantipur
No comments:
Post a Comment