In recent time, Rs. 160 million per MW has become a rule of thumb. Any project
above Rs. 160 million per MW seems to be less attractive. Thus, Rs. 160 per MW can
be regarded as a threshold for the current PPA rates with a design discharge of
Q40%.
The
threshold suggests us that the project becomes more attractive if it is below
Rs. 160 million per MW. In simple term, “the lower the project cost, the
better”.
But,
developers have a different idea. Below is a comparison of two new upcoming
projects.
Project Name
|
Khare
|
Super Dordi
|
Location
|
Dolakha
|
Lamjung
|
Type
|
RoR
|
RoR
|
Installed Capacity
|
24.1 MW
|
49.6 MW
|
Net Head
|
333.77 meters
|
584 meters
|
Design Discharge
|
8.43 m3/sec at
Q40%
|
9.9 m3/sec at Q40%
|
Total Sellable Energy
|
139.22 GWh
|
289.464 GWh
|
Status
|
Generation license
acquired, PPA signed, Financial Closure done.
|
Generation license
acquired, PPA signed, Financial Closure is ongoing
|
Length of weir
|
26.80 m
|
17 m
|
Side Intake (W X H)
|
3.6 m x 1.3 m, 2 Nos.
|
3.5 m x1.2 m, 3 Nos.
|
Desanding
|
61 m x 7 m x 6.02 m; 2
chambers
|
82m x 10m x 7.57 m; 2
chamber
|
Tunnel
|
4796 m
|
4864 m
|
Penstock
|
870 m
|
1185 m
|
Powerhouse (LxBxH)
|
35.70 m x 17.80 m x
25.65 m
|
45 m x 15 m x 10.2 m
|
Tailrace Canal
|
105.5 m
|
96.0 m
|
Transmission line
|
8.81 km
|
5.2 km
|
Cost
|
Rs. 3.922 billion
|
Rs. 8 billion (approx.)
|
Cost per MW
|
Rs. 162.7 million
|
Rs. 161.3 million
|
Super
Dordi is double in size compared to Khare. It is extremely high head project.
High head project has its own advantage. Theoretically, the cost per MW tends
to be at lower side in high head projects.
Now, if we look at the discharge, both the projects have similar design
discharges (9.9 and 8.43 cumecs). When you have a similar design discharge, the
size of the structures will also be similar. However, the length of the
structures might be different which will play a significant role in determining
the project cost.
Interestingly,
there is no night and day difference between these two projects when it comes
to the length of headrace tunnel, penstock pipe, tailrace and transmission
line. The structures to be constructed are more or less the same.
The
only significant difference in the total project cost will be undoubtedly in the
power house and the electro-mechanical heading. However, these headings will
either increase proportionately or increase in a decreasing trend due to
economies of scale. For instance, the cost per kilowatt for buying 10 MW
electro-mechanical equipment will be significantly lower compared to the cost
per kilowatt of 1 MW equipment.
At
last, what surprises me is the cost per MW of these projects. Both have similar per
MW cost. This, to me, is very weird.
I totally understand that hydropower project cost is very site specific. Infrastructures like access road play a major role. But I must say that I am fully aware of these parameters and have carefully chosen the ‘similar projects’ for this comparison.
I totally understand that hydropower project cost is very site specific. Infrastructures like access road play a major role. But I must say that I am fully aware of these parameters and have carefully chosen the ‘similar projects’ for this comparison.
Am I too suspicious or everyone is thinking what I am thinking at the moment?
कतै धनरासी व्र्रमलुट भएको अवस्था हो कि जस्तोछ ।
ReplyDelete