It
might be considered as a sin to talk about solar energy in Nepal. The country,
rich in hydro resources, is inclined to be blatantly loud and assertive in
self-defense. It is not everyone's cup of tea due to its expensive LCOE
(levelized cost of electricity). Name-calling is expected when you try to
explore the solar opportunity in this country.
Well,
things are about to change. The news about solar energy getting as cheap as US
30 dollar per megawatt-hour certainly raised some eyebrows in Nepal.
According
to newspapers, the main reason for such low LCOE is due to availability of
cheaper solar panels that are produced in China (China is now the largest
producer of solar panels in the world). The decline is also caused by a decline
in the cost of the inverters that convert the DC power produced by solar panels
to AC power for the grid.
The
low LCOE in international arena is surely a welcoming news for Nepal since many
Nepali are also keeping their eyes on this industry. And now, without further
ado, let's find out the opportunities and challenges of solar in Nepali
context.
Opportunities
Solar
is relatively a new concept here. It is limited to rooftop for residential
purposes only as of now. People started taking it seriously for commercial
energy generation only after the devastating earthquake that struck on
2015.
It
was last year when ‘National Energy Crisis Reduction and ElectricityDevelopment Decade’ was declared to end the energy crisis which announced ‘take
or pay’ PPA for solar for 25 years with a benchmark unit rate of NRs. 9.61 per
kWh for the first time. GoN aims to generate 10 percent of the total capacity
through solar and wind, i.e., roughly about 100 MW. Soon after, few solar
projects were awarded to private developers.
Challenges
The
first question that pops up in my mind 'is NRs. 9.61 per kWh reasonable enough
to make solar project feasible in present context?'
Yes,
it is highly feasible if we consider the above mentioned LCOE. But, considering
the Nepali market (the quoted price of solar panel by the local suppliers,
interest rate and other factors), the answer, however, seems to be complicated.
Assuming
300 days of sunshine a year with a daily solar radiation of 4.5 KWh/m2, one MWp
solar PV system will generate 1.35 GWh a year (very realistic). Therefore, the
ideal project cost would be in between NRs. 7 to 8 crores per MW in order to be
able to earn reasonable profits at NRs. 9.61 per kWh or let's say to be at par
with what Nepali hydropower is offering.
Having
quoted the ideal per MW cost for NRs. 9.61 per unit, it is, however, hard to
accurately forecast the project cost. There is a significant variability in
price of panels which varies from NRs. 40 per Watt to NRs. 75 per Watt. The
drastic variability in panel cost suggests us few things we need to consider.
First,
we do not have enough experiences in solar project so most of us have no idea
about the actual amount of energy that different solar modules/brands generate.
Second, solar panel degrades gradually. It's a fact. The amount of energy it
generates will decrease over time. The degrading rate can be 0.5 percent per
annum or a lot higher depending upon the quality of solar panels.
All
these considerations force us to go for a high quality solar panels. And now
assuming NRs. 75 per watt as a top notch quality in terms of energy generation,
1 MWp would cost around NRs. 20 crores (higher price is equal to higher quality
and higher energy generation, a layman's thinking). It is no way near the cost
I quoted earlier. At this cost, I reckon that the unit rate should be around
NRs. 25.
S.N.
|
Cost Component of Solar PV
|
Percentage
|
1
|
PV Module
|
69%
|
2
|
Array Supporting Structures
|
|
3
|
PV String Junction Box
|
|
4
|
PV String Combiner Box
|
|
5
|
PV On Grid Inverter
|
|
6
|
AC Combiner Box
|
|
7
|
Cables, Conduits and Accessories (DC and AC)
|
|
8
|
Circuit Breakers, Isolators, Surge Protectors
etc.
|
|
9
|
Earthing and Protections
|
|
10
|
Monitoring System
|
|
11
|
Transportation of Equipments (Local)
|
|
12
|
Civil Works
|
|
13
|
Protection Fence and Gate
|
|
14
|
Installation, Testing and Commissioning
|
|
15
|
Transmission Line and electrical works
|
25%
|
16
|
Land Acquisition Cost
|
1%
|
17 |
Miscellaneous Cost
|
5%
|
Total
|
NRs. 20 crores
|
* It
is important to note that the solar PV project costs are also site specific
like hydropower projects and depends on various factors such as length of
transmission lines, cost of land, infrastructure and so on. I have ruled out
the option of installing solar project in urban areas due to higher value of
land. The rule of thumb says a MW scale solar project requires about 30 ropanis
of land.
The
other challenge is the location. GoN has issued several survey licenses for
solar recently. But, almost all projects are in Terai belt. Data have shown
that solar radiation is higher in mountainous regions of Nepal than Terai.
List of Survey license awarded by DoED in the past 6 months
S. N.
|
Developers
|
Capacity (MW)
|
Location
|
1
|
KTM Energy Pvt. Ltd
|
10
|
Morang
|
2
|
KTM Energy Pvt. Ltd
|
5
|
Morang
|
3
|
KTM Energy Pvt. Ltd
|
10
|
Morang
|
4
|
NEA
|
8.3
|
Nuwakot
|
5
|
NEA
|
3.5
|
Nuwakot
|
6
|
NEA
|
8.1
|
Nuwakot
|
7
|
Api Power Company Ltd.
|
1
|
Bardaghat
|
8
|
Api Power Company Ltd.
|
1
|
Dhalkebar
|
9
|
Api Power Company Ltd.
|
0.5
|
Kawasoti
|
10
|
Api Power Company Ltd.
|
1
|
Kawasoti
|
11
|
Api Power Company Ltd.
|
1
|
Simara
|
12
|
Api Hydro-mechanical Pvt. Ltd
|
1.5
|
Duhabi
|
13
|
Ridi Hydropower Development Company Ltd
|
8.5
|
Butwal
|
14
|
Api Power Company Ltd.
|
4
|
Chandranigahpur
|
15
|
Api Power Company Ltd.
|
1.5
|
Chanauta
|
16
|
Api Power Company Ltd.
|
8
|
Parwanipur
|
17
|
Asian Tech Corporation Pvt. Ltd.
|
4
|
Lahan
|
18
|
Clean Communication Pvt. Ltd
|
4
|
Hetauda
|
19
|
Global Energy & Construction Pvt. Ltd.
|
8
|
Duhabi
|
20
|
Gorkha Congenial Energy & Investment Pvt.
Ltd.
|
3
|
Lamahi
|
21
|
Kantipur Energy Investment & Construction
Pvt. Ltd.
|
2
|
Anarmani
|
22
|
Kantipur Energy Investment & Construction
Pvt. Ltd.
|
2
|
Anarmani
|
23
|
Kantipur Energy Investment & Construction
Pvt. Ltd.
|
1.5
|
Birgunj
|
24
|
Kantipur Energy Investment & Construction
Pvt. Ltd.
|
2
|
Birgunj
|
25
|
Kantipur Energy Investment & Construction
Pvt. Ltd.
|
2.5
|
Damak
|
26
|
Sagarmatha Energy & Construction Pvt. Ltd.
|
3
|
Dhalkebar
|
27
|
Asian Tech Corporation Pvt. Ltd.
|
1
|
Lahan
|
Total
|
105.9
|
Conclusion
Although
I feel like GoN declared the solar unit price without a proper research but the
recent progress has opened up a huge opportunity for Nepali investors. It seems
like solar has a good future ahead.
P.S.
This post is not about Hydro Vs Solar.
Lets hear your thoughts on the new "Nepalko pani jantako lagani" scheme of Energy minister Janardan Sharma and his methodology.
ReplyDeleteyour articles are great.
ReplyDeleteAll Knowledge
ReplyDelete