The total loan and advance of Nepalese commercial banks
stood at NRs. 1,801.567 billion at the end of Ashwin 2074 or mid October, 2017 (source: NRB). With
5% minimum lending requirement in hydropower sector as provisioned by Central
Bank of Nepal, the total loan available is NRs. 90.078 billion. On the other
hand, hydropower projects with install capacity of 2,043.6 MW have done the
financial closure while 910.31 MW are in the process of securing debt (NEA’s Annual Report 2017). Assuming NRs. 180 million per MW as the construction cost,
and 70:30 as Debt equity ratio, the total loan requirement is NRs. 372.19
billion. Even at the 10% as minimum lending requirement (assuming that Central
bank will increase the provision), the total funds available will be around
NRs. 180.157 billion.
Projects at
various stages
Details
|
MW
|
FC completed
|
2,043.613
|
Under FC
|
910.311
|
Total
|
2,953.924
|
Source: NEA’s Annual Report 2017
Required fund
Details
|
Amount
in NRs. Billion |
Fund required @ NRs. 180 million
per MW |
531.71
|
Total Loan Requirement (70%)
|
372.19
|
Total Equity Requirement (30%)
|
159.51
|
Available fund
Details
|
Amount
in NRs.
Billion |
Total Loan of Commercial
Bank as of Ashwin 2074 |
1,802
|
5%
|
90.078
|
10%
|
180.157
|
The figures clearly show that there is a huge deficit in
domestic financing for hydropower projects.
In such situation, FDI seems to be the only option if we
are to develop the projects that have done the financial closure and the
projects that are in the process of doing so.
Well, there are some positive signals for foreign
investor such as introduction of dollar PPA for projects above 100 MW. However,
majority of the projects (2,953.924 MW) are below 100 MW, and every Nepali
hydropower professional by now knows ‘without dollar PPA, no investor (loan
investor) will invest’.
Policy makers of Nepal should understand the
technicality of hydropower revenue stream. Unlike foreign investors in hotels and
trading businesses where the business owners have the advantages of increasing
their selling price and sales volume in order to mitigate the forex risk,
hydropower owners lack such benefits.
Its revenue is fixed for the entire PPA period. Any fluctuation in the
foreign exchange rate will directly affect the repayment schedule. On top of
that, our currency is peg with Indian currency (IRs. 1 = NRs. 1.60). What if in
one fine morning, the peg is revised to IRs.1 = NRs. 2? I don’t think anyone
who opposes dollar PPA has answer to this question.
For years, our policy makers have urged not to sign
dollar PPA but one thing I never understand. When everything we import is paid
in USD, why there is so much fuss when it comes to dollar PPA?
The equation is very simple. If we do not sign dollar PPA
then forget about constructing 17,000 MW in 10 years. We will not be able to
realize all the projects (2,953.924 MW) that have done the financial closure
and the projects that are in the process of doing so.
In addition to
dollar PPA, the PPA regime that we are now adopting needs some modifications if
we are to attract investment in fast track. Many foreign investors do not want
to lock their investment for a long period of time. In order to better
understand what I am trying to say, let me throw some figures.
Projects
|
Capacity
|
Investor
|
Per MW
construction cost |
Upper Marsyangdi
|
50 MW
|
Chinese
|
NRs. 320 million
|
Upper Trishuli 1
|
216 MW
|
Korean
|
NRs. 280 million
|
Kabeli A
|
37.6 MW
|
World Bank
|
NRs. 297 million
|
The above projects are owned/invested by foreign
investors. If we look at their per MW cost, they tend to construct the projects
in the range of NRs. 300 million per MW against NRs. 180 million per MW by the
local developers. The figure suggests that foreign investors are not here to
collect dividend after the operation.
Fair enough! If this is the case, why not to give another
option to those investors who do not have patience to wait for a longer period to
recoup their investment? For instance, 10 years PPA option.
Currently, the PPA rate for RoR project is NRs. 5.88 per
kWh (NRs. 4.80 x 0.7 + NRs. 8.40 x 0.3) in the first year of operation. There
are 8 escalations at 3 percent (simple). From the ninth year of operation, it
reaches to NRs. 7.29 per kWh and remains constant until the project is handed
over to government of Nepal at free of cost (after 30 years of operation from
Commercial Operation Date, the project has to be returned to Nepal Government).
Year
|
Existing
PPA rates per kWh (NRs.) |
Proposed
PPA rates per kWh (NRs.) |
1
|
5.88
|
12
|
2
|
6.06
|
12.36
|
3
|
6.23
|
12.72
|
4
|
6.41
|
13.08
|
5
|
6.59
|
13.44
|
6
|
6.76
|
13.80
|
7
|
6.94
|
14.16
|
8
|
7.11
|
14.52
|
9
|
7.29
|
14.88
|
10
|
7.29
|
14.88
|
11
|
7.29
|
|
12
|
7.29
|
|
13
|
7.29
|
|
14
|
7.29
|
|
15
|
7.29
|
|
16
|
7.29
|
|
17
|
7.29
|
|
18
|
7.29
|
|
19
|
7.29
|
|
20
|
7.29
|
|
21
|
7.29
|
|
22
|
7.29
|
|
23
|
7.29
|
|
24
|
7.29
|
|
25
|
7.29
|
|
26
|
7.29
|
|
27
|
7.29
|
|
28
|
7.29
|
|
29
|
7.29
|
|
30
|
7.29
|
|
Total
|
212.39
|
135.84
|
Let’s introduce 10 years PPA model in addition to 30
years. Although the rate seems to be more than double, the actual amount Nepal
government is going to pay will be reduced to almost half (NRs. 212.39 vs NRs. 135.84).
Now the question lies, will they be attracted? For this,
let’s do a simple assessment.
Practical Assumptions.
Plant Factor
|
60%
|
Debt: Equity
|
80:20
|
Repayment
|
8 years
|
First Year Revenue per MW
|
Annual
Royalty + O&M per MW |
NRs. 63,072,000
|
NRs. 2,361,440
|
Repayment of Loan
Loan
Amount per
MW
(NRs.)
|
Annual
Average
(P+I) @ 4%
|
Annual
Average
(P+I) @ 5%
|
Annual
Average
(P+I) @ 6%
|
300,000,000
|
43,881,391
|
45,575,712
|
47,309,149
|
DSCR
|
1.38
|
1.33
|
1.28
|
Loan
Amount per
MW
(NRs.)
|
Annual
Average
(P+I) @ 4%
|
Annual
Average
(P+I) @ 5%
|
Annual
Average
(P+I) @ 6%
|
350,000,000
|
51,194,956
|
53,171,664
|
55,194,007
|
DSCR
|
1.19
|
1.14
|
1.10
|
By looking at the figures, I am pretty sure we will be
able to attract a lot of investors by this adopting model. It is not a bad model, is it?
Very informative. You did the hard work.. Hats off.
ReplyDeleteIt has been great to know that there is someone out there that knows about falling down and getting back up. We always stay humble and never give up, and for the help of Mr Pedro in getting me Loan from his firm to expand my business, at a pivotal time. The support I received from his loan firm was quite honest and an interesting low rate in return, Mr Pedro Jerome is a loan officer working with a loan company which is willing to fund any type of business or give loans for personal use as long as their repayment is guaranteed.
ReplyDeleteYou can contact theirs email on pedroloanss@gmail.com Via WhatsApp:+1-863-231-0632