The tendency of our Nepali experts introducing new
policies without analyzing the impact and crunching numbers is something I have
never understood. I wonder if they ever do analysis beforehand (most probably,
they don’t).
Five years back, I
pointed out that hydropower will be the next disaster. The main reason for that
conclusion was due to low PPA rates and lack of a regulatory body (It is
proving to be so true)
Now, whenever I come across with new hydropower project,
the first thing I question is the profitability. No project excites me to open
my wallet in recent times. All projects seem to be below average and disappointing.
It looks like the general investors have become the “scapegoats” big time.
Had our policy makers been addressing the mismatch
between the PPA rates and the construction cost earlier and establishing a
regulatory body for hydropower, the situation would not have occurred. Any
measures introduced now to make the correction will not have significant impact.
The damage has been done already. People have already invested huge amount in
hydro shares that is as good as garbage.
The second point I want to make is regarding the hydropower
scheme. The need of the country is the reservoir and Pondage RoR. Until
recently, we did not have the PPA rates for these schemes. Now, we have the PPA
rates, but it is already too late. All the accessible projects (close to road
and transmission line) are awarded to developers, and almost all projects are
RoR scheme. In order to get fresh license for PRoR (particularly) and storage, developers
have to go upstream. However, developers will not be able to design the project
in PRoR as the projects downstream (mostly RoR) will be affected directly. Change
in hydrology of the river will have negative impact on electricity generation
of downstream projects. This is why Sinohydro Sagarmatha, the developer of the
50 MW Upper Marshyangdi-A Hydropower Project, has recently sought assurances
from the government that its project will not be affected by 600 MW Upper
Marshyangdi-2 Hydroelectric Project (PRoR scheme).
This proves that our policy makers have failed in this
aspect too. There is literally no chance for new PRoR project in Nepal as all
river basins are awarded to RoR developers already.
Another likely mistake of our policy makers is the going
to be 100 MW mark. I do not know the reason behind the 100 MW but it looks
likely all the new policies will be applicable for projects above 100 MW only.
For instance, introduction of dollar PPA for projects above 100 MW. Also the
concept paper regarding hedging service of Nepal Rastra Bank says that energy
projects above 100 MW will qualify for the hedging service. Here, practicality
seems to be lacking.
If you go through the NEA’s Annual Report, the total
install capacity with financial closure is 2,043.6 MW while 910.31 MW are in
the process of securing debt. However, almost all projects are below 100 MW. On
the other hand, our financing capacity is not sufficient to meet half of these
projects. In such case, developer’s option to seek foreign debt is also ruled out
due to 100 MW cap. Secondly, it rules out the option of EPC-F which in recent
times is becoming more popular in Nepali hydro industry. The basic idea of
EPC-F is to construct the project by foreign contractor (mainly Chinese in
Nepali context) with their own financial resource and pay the contractors their
full value at the end of construction at one time which involves FOREX risk that
requires hedging for mitigation. Since most of the projects are below 100 MW
size, the rule of 100 MW is going to affect the hydropower construction big
time especially for those who are exploring to secure debt from abroad and for
those who are looking for EPC-F model for hydropower construction.
No comments:
Post a Comment