Tuesday, 8 January 2019

Upper Trishuli 1 Dollar Exchange Risk Explained


While Nepal government is all set to organize another investment summit, Nepal Water and Electricity Development Company (Korean) has threatened to pull out from Nepal after the government asked it to contribute a hefty sum to a hedge fund to be used as a cushion against exchange risk. According to newspaper, the Korean company is ready to contribute only USD 5 million. I was curious if it is sufficient to cover the exchange risk.

Sunday, 12 August 2018

Blunders : one after another


The tendency of our Nepali experts introducing new policies without analyzing the impact and crunching numbers is something I have never understood. I wonder if they ever do analysis beforehand (most probably, they don’t).

Wednesday, 1 August 2018

HIDCL’s right share proposal


Hydroelectricity Investment and Development Limited (HIDCL) has notified Nepal Stock Exchange (NEPSE) regarding the issuance of its 100% right share.

Friday, 6 July 2018

Upper Tamakoshi – a reality check for much hyped hydropower?


After long delays due to various reasons, Upper Tamakoshi is now all set to float its local shares. According to its invitation letter, the projected cost is estimated to be Rs. 66.08 billion. This makes per MW cost of Rs. 14.49 crore. Although the per MW seems to be at the lower side compared to recent market trend (above Rs. 20 crore), the project, however, will not able to keep up its hype due to its lower PPA rate which is at Rs. 4.06 per kWh (average) for the first year.

Wednesday, 7 March 2018

Compensation clause for 30% dry energy.



With new guidelines effective from this year, there is an option of 30% dry energy for RoR projects. In this option, hydropower projects will receive NRs. 8.40 per kWh for six months (Mangsir 16 – Jestha 15) and NRs. 4.80 for the remaining 6 months (Jestha-16 to Mangsir 15). However, the total dry energy should be more than 30% of the total energy supplied. Any projects suppling dry energy below 30% will be penalized. The formula for such compensation to NEA will be the following

Wednesday, 28 February 2018

Vicious Cycle and ways to overcome it



It is needless to say that we have not been able to harness 2% of the total hydro potential. With a stable government on the horizon, I think it is the right time to debate on how to exploit our resources.

Friday, 9 February 2018

Financing capacities of Nepali banks



The total loan and advance of Nepalese commercial banks stood at NRs. 1,801.567 billion at the end of Ashwin 2074 or mid October, 2017 (source: NRB). With 5% minimum lending requirement in hydropower sector as provisioned by Central Bank of Nepal, the total loan available is NRs. 90.078 billion. On the other hand, hydropower projects with install capacity of 2,043.6 MW have done the financial closure while 910.31 MW are in the process of securing debt (NEA’s Annual Report 2017). Assuming NRs. 180 million per MW as the construction cost, and 70:30 as Debt equity ratio, the total loan requirement is NRs. 372.19 billion. Even at the 10% as minimum lending requirement (assuming that Central bank will increase the provision), the total funds available will be around NRs. 180.157 billion.

Monday, 22 January 2018

West Seti Hydropower in limbo

It looks like another company is going to pack its bag. China Three Gorges International Corporation, the potential builder of West Seti Hydropower Project (750 MW), showed dissatisfaction over the Power Purchase Rate Policy proposed by Nepal Government. Storage project like West Seti is entitled to receive NRs. 12.40 per kWh and NRs. 7.10 per kWh during dry and wet season respectively.

Thursday, 4 January 2018

Budhigandaki vs Upper Karnali vs Arun 3

In a country like Nepal where financial resource is scarce, we have no other option than use it wisely to get optimum benefits. However, things are not applied in Nepal as learned in economic class during our uni days.

Wednesday, 8 November 2017

Election Manifesto

Having a huge hydropower potential, all politicians, policy makers and experts have come to a common understanding that hydropower development is a key determinant of the growth potential of Nepali economy. As such, all major political parties have declared to exploit the hydro resources in their election manifestos.

Friday, 4 August 2017

Rates for Peaking Run of River

Developers of peaking run of river hydropower project can enjoy better rates. Developer will be entitled to receive Rs. 8.50 to Rs. 10.55 per unit.

Tuesday, 13 June 2017

Take or Pay PPA

NEA has recently changed the “Take and Pay PPA” to “Take or Pay PPA” All projects including those which have "Take and Pay PPA" are entitled for the amendment provided their Commercial Operation Date (COD) is before mid-July 2026 AD.

Thursday, 8 June 2017

PPA IN DOLLAR Too Little Too Late

At a time when the government has announced an ambitious plan to generate 20,000 MW of electricity within a decade, there is the need of a huge foreign investment to fulfill the objective. To lure foreign investment, there is the need to sign the PPA in dollars.

Wednesday, 19 April 2017

Paradigm Shift

Nepal’s hydro is predominately RoR schemes and almost all pipeline hydropower projects are also RoR.

Monday, 13 March 2017

Foreign Investment Climate

All of a sudden Nepal has been bombarded by summits. In the past few months, different organizers have held several investment/infrastructure summits so hastily. The objective of those summits was to attract foreign investment in the country but the outcomes were not that satisfactory. However, ‘Investment Summit 2017’ organized by Investment Board, Nepal last week did draw world’s attention. Investors pledged a jaw-dropping FDI commitment of US $ 13.51 billion.

Sunday, 5 March 2017

Govt plans to consider six months as dry season

Government plans to increase dry season period to six months from four months. This certainly is a good news for IPPs as the RoR projects will be entitled to get dry season rate (Rs. 8.40 per kWh) for six months (December to May). However, it comes with a clause which to me is useless and is not in the favor of project and the country as a whole.

Sunday, 8 January 2017

Solar through my lens!



It might be considered as a sin to talk about solar energy in Nepal. The country, rich in hydro resources, is inclined to be blatantly loud and assertive in self-defense. It is not everyone's cup of tea due to its expensive LCOE (levelized cost of electricity). Name-calling is expected when you try to explore the solar opportunity in this country. 

Tuesday, 13 December 2016

Kulman Ghising: sheer luck or calculated risk?



All these years we thought that there is a huge mismatch between demand and supply of electricity. Load shedding for 12 to 16 hours a day during dry season was quite common and we were prepared for the same thing this year too.

Thursday, 8 December 2016

Indian policy discourages non-Indian hydropower investors



KATHMANDU, Nov 8: India has brought cross border electricity trading policy to facilitate energy trading with neighboring countries. 

Wednesday, 19 October 2016

IPO of Arun Kabeli Power Limited



Arun Kabeli Power Limited is the next hydropower company that is going to be listed in Nepal Stock Exchange. Here is my sincere opinion regarding the Company, its project and speculated share price when listed in Nepal Stock Exchange.