Here
is my speculation and the review of Upper Tamakoshi Hydro Electricity Project.
For latest assessment, please visit Upper Tamakoshi – a reality check for much hyped hydropower?
1)
GENERAL BACKGROUND
Upper Tamakoshi Hydro Electricity
Project (UTHEP) is the largest hydropower project being constructed in the
country so far. It is located in Dolkha District, 197 km east of the capital
Kathmandu.
The project is conceived as a peaking
run-of-river project with an 822 gross head, a design discharge of 66 m3/s and
an installed capacity of 456 MW.
The major components of this project are
the intake, a 22 m high concrete dam, twin desanding basins, a 9.4 km headrace
tunnel, an underground powerhouse with six Pelton turbines, a 2.9 km long
tailrace tunnel, and a 47 km long 220 kV transmission line to Khimti
substation. Additionally, around 4 km of adit tunnel has to be constructed.
The project has an authorized capital of
NPR. 11 billion and the issued capital is NPR. 10.59 billion.
Authorized Capital
|
NPR. 11,000,000,000
|
Issued Capital
|
NPR. 10,590,000,000
|
It
is developed by Nepal Electricity Authority (NEA). The actual shareholding of
this project is as below.
Shareholders
|
No. of Shares
|
%
|
Amount (NPR)
|
|
Promoter
|
Nepal Electricity
Authority
|
43,419,000
|
41%
|
4,341,900,000
|
Nepal Telecom
|
6,354,000
|
6%
|
635,400,000
|
|
Rastriya Beema
Sansthan
|
2,118,000
|
2%
|
211,800,000
|
|
Citizen Investment
Trust
|
2,118,000
|
2%
|
211,800,000
|
|
Ordinary
|
Local (Resident of
Dolkha District)
|
10,590,000
|
10%
|
1,059,000,000
|
Depositors of EPF
|
18,299,520
|
17.28%
|
1,829,952,000
|
|
Employee of EPF, CIT,
NTC, Rastriya Beema Sansthan
|
3,049,920
|
2.88%
|
304,992,000
|
|
Employee of NEA and
Upper Tamakoshi
|
4,066,560
|
3.84%
|
406,656,000
|
|
General Public
|
15,885,000
|
15%
|
1,588,500,000
|
|
Total
|
105,900,000
|
100%
|
10,590,000,000
|
Salient Features of the Project
Type of Hydropower
|
Peaking Run-of-River (PRoR)
|
Location
|
Lamabagar VDC, Dolkha District, Janakpur Zone, Nepal
|
Headworks Location
|
Lamabagar VDC
|
Powerhouse Location
|
Gongar Gaon, Lamabagar VDC
|
Catchment Area
|
1,745 sq. km.
|
Gross Head
|
822 m
|
Installed Capacity
|
456 MW
|
Annual Energy
|
2,381 GWh
|
Design Discharge
|
66.0 m3/sec
|
Headrace Tunnel
|
8.4 km
|
Penstock
|
1134 m
|
Tailrace Tunnel
|
2.9 km
|
Access Road from
Charikot
|
68 km
|
No. of Units
|
6
|
Transmission line
|
220 kVA Double Circuit, 47 km (Gongar to Khimti Substation)
|
Construction Cost
|
NRs 35.29 excluding IDC
|
The total investment of this project is
raised through a mixture equity and debt. The total equity investment will be NPR.
10.59 billion. NPR. 20 billion will be financed by EPF, CIT, RBS and NT. Besides
these institutions, Government of Nepal has assured NPR. 11.08 billion as a gap funding during construction.
Debt
Lending Instiutions
|
Amount
|
Employee Provident Fund
|
10,000,000,000
|
Citizen Investment
Trust
|
2,000,000,000
|
Rastriya Beema
Sansthan
|
2,000,000,000
|
Nepal Telecom
|
6,000,000,000
|
Nepal Government
|
11,080,000,000
|
Total
|
31,080,000,000
|
The
debt will carry 11 percent interest rate that can be revised mutually.
2)
PROJECT STATUS
The project is located in Dolakha
district. The basic infrastructures required for the project construction like
land and road have been already purchased/constructed. The construction of
civil works, headrace tunnel is in the full swing. 80 percent of the tunnel
work has been completed till date. Import of machinery and installation is
taking place. In overall figures, the project has completed 71 percentage so
far. And in amount, the project has already spent NPR. 21 billion.
The project will come into operation
phase wise. Out of six units, the first unit will start generation from Shrawan
2073 B.S. (July 2016). All the remaining units will start generation by Poush
2073 B.S. (December 2016)
MY
OPINION:- The project will be able to achieve its
target unless the project faces unexpected technical difficulties, particularly
in tunnel. After all it has got support from every corner.
3) PROJECT FEATURES
Technical Features
a) Project Cost:- The project
will be the lowest cost project in Nepal. Thanks to its head which is above 800
meters. The cost per MW is NPR. 77.39 million without interest during
construction (IDC). Even with IDC, the cost per MW is around NPR. 90 million
which is considered as one of the cheapest project in Nepal. Currently, the
cost per MW is around NRs. 160 to NPR 180 million.
MY
OPINION:-
Total cost of the project is at lower
side which is always nice.
b)Electro-mechanical equipment:- The project
will install electro-mechanical equipment supplied by Andritz Hydro GmbH, an
Austrian company. Andritz has a high reputation of producing efficient
equipments.
MY
OPINION:-
Efficiency of machinery is ensured. This
will reduce the annual cost of repair and maintenance and will deliver the
contract energy.
c)
Energy:- The total
yearly output is 2,381 GHw which will be sold to NEA. This makes Plant Load
Factor (PLF) of 59.76 percent. In layman term “the higher the PLF, the better”.
PLF represents the percentage of total sellable energy compared to its actual
plant capacity. The industry standard is around 60 percent.
MY
OPINION:- The PLF is 59.76
percent which is also the industry standard (59.76% is almost 60%).
d)Transmission Line:- The power will
be evacuated through a 47 km long double circuit 220 kV transmission line at Khimti substation which will be connected to 75 km
Khimti-Dhalkebar substation. Khimti-Dhalkebar 220 kV transmission line is
funded by World Bank. Of the 188 towers, 180 have been already constructed.
MY
OPINION:- Although there
are some protest made by locals for the construction of new substation for
power evacuation, it is safe to say that the completion of transmission line and
substation will be on time since this project is highly prioritized by Nepal
government.
Emotional Features
Upper Tamakoshi is a national level
project which will be funded entirely through Nepalese people and Nepalese
organizations. This is the biggest hydropower project in Nepal so far and the
completion of national pride project is expected to reduce load-shedding
significantly.
Financials
a) PPA Rates:- As per Power
Purchase Agreement, the NEA will buy energy at a flat rate of NPR. 4.06 per kWh
during the first year of operation. There is an escalation of 3 percent for the
first 9 years. From 10th year, NEA will buy energy at a flat rate of
NPR. 5.30 per kWh which will remain constant throughout the entire license
period.
MY
OPINION:-
By looking at the PPA rate, Upper
Tamakoshi PPA rate is at lower side. Currently, NEA buys energy at NPR. 4.80
and NPR 8.40 per kWh during wet season and dry season respectively. This makes
an average of about NPR. 5.10 per kWh in the first year of operation which will
increase to NPR. 6.10 per kWh in the sixth year (it remains constant
afterwards).
b) Revenue:- The first year
revenue of the project from the sale of energy is estimated at NPR. 9.66
billion which increases to NPR 12.6 billion in 10th year and remains
constant throughout the license tenure.
MY
OPINION:- NPR. 9.66
billion is the first year income which increases to NPR.12.6 billion over the
years. The total equity investment is NPR. 10.59 billion. This is outstanding.
However, this could have been even better if it had managed to get the standard PPA
rate (NPR. 4.80 per kWh during wet season and NPR. 8.40 per kWh during dry
season). The first year income could have been over NPR. 12 billion.
c) Indicators
Project IRR
|
25.2%
|
Equity IRR
|
59.0%
|
NPV at 11%
|
47,264,862,060
|
B/C Ratio (11%)
|
2.14
|
MY
OPNION:- IRR industry
average in Nepalese hydro is around 16 percent while equity IRR is in
between 20 to 25 percent. The indicators of Upper Tamakoshi simply surpass these
averages.
d) Projection
Profit and loss account (in million)
Particulars/Year
|
1
|
2
|
3
|
4
|
5
|
Total Energy in GHh
|
2,381
|
2,381
|
2,381
|
2,381
|
2,381
|
Price per kWh
|
4.06
|
4.18
|
4.31
|
4.44
|
4.57
|
Income from Energy Sale
|
9,667
|
9,957
|
10,256
|
10,563
|
10,880
|
Government Subsidy
|
2,280
|
||||
Less:
|
|||||
Operation and Maintenance Cost
|
104
|
106
|
108
|
110
|
112
|
Royalty
|
285
|
290
|
296
|
302
|
309
|
Interest on Debt
|
3,381
|
3,281
|
3,169
|
3,045
|
2,906
|
Depreciation
|
1,107
|
1,107
|
1,107
|
1,107
|
1,107
|
Total Expenses
|
4,876
|
4,783
|
4,680
|
4,564
|
4,433
|
Profit Before Bonus & Tax
|
7,071
|
5,173
|
5,576
|
5,999
|
6,447
|
Less:
|
|||||
Bonus & Welfare Fund
|
141
|
103
|
111
|
120
|
129
|
Profit Before Tax
|
6,930
|
5,070
|
5,464
|
5,879
|
6,318
|
Less:
|
|||||
Tax
|
-
|
-
|
-
|
-
|
-
|
Profit After Tax
|
6,930
|
5,070
|
5,464
|
5,879
|
6,318
|
Dividend to Shareholders
|
5,295
|
4,236
|
4,236
|
5,295
|
5,295
|
Reserve Transfer to BS
|
1,635
|
834
|
1,228
|
584
|
1,023
|
Total Reserve in BS
|
1,635
|
2,469
|
3,697
|
4,281
|
5,304
|
Number of Shares in million
|
106
|
106
|
106
|
106
|
106
|
EPS
|
65.44
|
47.87
|
51.60
|
55.52
|
59.66
|
DPS
|
50%
|
40%
|
40%
|
50%
|
50%
|
Cash flow (in million)
Particulars/Year
|
1
|
2
|
3
|
4
|
5
|
Receipt
|
|||||
Opening Balance
|
-
|
7,172
|
7,090
|
8,349
|
9,899
|
Net Profit Before Tax
|
6,930
|
5,070
|
5,464
|
5,879
|
6,317
|
Add: Depreciation
|
1,107
|
1,107
|
1,107
|
1,107
|
1,107
|
Sale of Fixed Assets
|
-
|
-
|
-
|
-
|
-
|
Total Receipt
|
8,036
|
13,349
|
13,660
|
15,335
|
17,323
|
Payments
|
|||||
Loan Re-payment
|
864
|
964
|
1,076
|
1,200
|
1,339
|
Tax
|
-
|
-
|
-
|
-
|
-
|
Dividend
|
-
|
5,295
|
4,236
|
4,236
|
5,295
|
E&M Replacement
|
|||||
Payment to Liabilities
|
-
|
-
|
-
|
-
|
-
|
Total Payment
|
864
|
6,259
|
5,312
|
5,436
|
6,634
|
Closing Balance
|
7,172
|
7,090
|
8,349
|
9,899
|
10,689
|
MY
OPNION:- Above figures speak all. Cash
dividend of 50 percent is possible in the first year of operation and I found
positive cash flow even if the company decides to pay the dividend at my rates.
* The projection is based on the standard
norms applicable for Nepalese hydropower. However, I have included NPR 5 million
per MW as a subsidy amount that was announced by Government of Nepal.
4) FUTURE PROJECTS
The company has planned to develop
hydropower projects in Tamakoshi River basin. After the completion of Upper
Tamakoshi project, it is planning to divert the Rolwaling river to the Upper
Tamakoshi intake which will increase the energy production. Also, the company
has obtained the survey license of of Tamakoshi V (100 MW) and Upper Tamakoshi
A HEP 45 MW. It has planned to develop these projects in future.
MY
OPINION:-
This is where I see the problem.
Generally, hydropower companies go for bigger projects once they construct a
project. Hydropower companies have to go that way since projects are
constructed in BOOT model. But this company does not have bigger projects in
future. If you look at the financial, Upper Tamakoshi will have a cash reserve
of around 10.7 billion at the end of fifth year even after distributing cash
dividend of around 50 percent per year. NPR. 10.7 billion is enough equity to
develop a project with a capacity of 400 MW.
5) IPO
Without any doubt, Upper Tamakoshi IPO
is the much awaited IPO in the history of Nepal.
10 percent of total issued capital or 10,590,000 shares have been allocated to the resident of Dolkha district. The maximum number of shares one can apply in this category is 70.
10 percent of total issued capital or 10,590,000 shares have been allocated to the resident of Dolkha district. The maximum number of shares one can apply in this category is 70.
Similarly,
24 percent of the total issued capital or 25,416,000 shares have been reserved
to the employee of Nepal Electricity Authority, Upper Tamakoshi Hydropower
Company, Employee Provident Fund, Citizen Investment Trust, Nepal
Telecommunication, Rastriya Beema Sansthan and the depositors of Employee
Provident Fund. In this category, one can apply up to five thousand shares.
Applications for these two categories have
already started. Please be informed that the shareholder of these categories
will have a lock-in period of three years from the date of allotment.
The final category is for general people.
15 percent of the total issued capital or 15,885,000 shares will be floated
to general public.
As for the timing, IPO for general
public will start within 6 months from now.
6) Share Price Speculation
No doubt, the application for share will
be oversubscribed. I will be surprised if Upper Tamakoshi IPO does not make any
record when it is floated in the market.
Some analyst are predicting that the
share price of Upper tamakoshi will be around NPR 5,000 (NPR. 100 is the face
value).
I believe there are so many factors
rather than mere speculation.
a) Price earning ratio:- The industry
average for Nepalese hydropower is around 40. If we multiply the projected EPS
of Upper Tamakoshi by 40, then it is safe to say that (65x40) NPR 2,600 is the
safe bet.
b) Demand and supply factor:- This will also play an important factor
for determining the share price. Locals can apply up to 70 shares each and the
employees and depositor of EPF can apply up to 5,000 shares. Similarly, general
public are eagerly waiting for this IPO. I believe shares will be scattered among
millions of investors. But the actual number of shares held by an individual will
be less. So imagine buying 1,000 shares in secondary market when it is listed in
Nepal Stock Exchange. I bet you will find hard getting that number. This will
certainly increase the share price.
MY
OPINION:-
By analyzing the current market situation
and the financial of the company, I would say it is safe to say that the share
price will stay at NPR 3,000. However, to maintain this price is a challenge.
As I mentioned earlier, the main drawback is the future projects. As of now,
Upper Tamakoshi does not have bigger projects in future. There is a risk that
Upper Tamakoshi might be sitting in a big pile of idle cash without much
prospect for investment.
MY FINAL VERDICT:- If you stick an air pump into the Chilime hydropower and blow up as hard as you can, you will end up with upper tamakoshi. Yes, the project size and structures are big but the ratios are literally the same. It is very very safe to say that Upper tamakoshi share will be no less than the share price of Chilime hydropower. This means, investors can expect handsome return. And yes, this project will help to minimize the load shedding in the country when it comes into generation in 2016. Overall, this project has a lot to offer in terms of financial return to investors and energy to the country.
MY FINAL VERDICT:- If you stick an air pump into the Chilime hydropower and blow up as hard as you can, you will end up with upper tamakoshi. Yes, the project size and structures are big but the ratios are literally the same. It is very very safe to say that Upper tamakoshi share will be no less than the share price of Chilime hydropower. This means, investors can expect handsome return. And yes, this project will help to minimize the load shedding in the country when it comes into generation in 2016. Overall, this project has a lot to offer in terms of financial return to investors and energy to the country.
For similar reviews, please click the following link.
IPO of Barun Hydropower Company Limited
The next upcoming IPO: Api Power Company Limited.
It is big and it is coming: HIDCL’s IPO
United Modi Hydropower Limited: IPO analysis.
IPO of Ngadi Group Power Limited
Happy Investing!
Interesting and Insightful information on Project financials and other aspects, something I have not seen before of Nepali ventures. Kudos !
ReplyDeleteInteresting...
ReplyDeleteNice read!
ReplyDeleteGood Read
ReplyDeletethis is the most delightful and meaning ful understandable review i get..thank u so much and keep up the good work....cheers!!
ReplyDeletegood one!
ReplyDeletewhat is the expected capacity during the dry season?
ReplyDeletewhy the cost of this project is low?
ReplyDelete