Wednesday, 19 October 2016

IPO of Arun Kabeli Power Limited



Arun Kabeli Power Limited is the next hydropower company that is going to be listed in Nepal Stock Exchange. Here is my sincere opinion regarding the Company, its project and speculated share price when listed in Nepal Stock Exchange.



1) PROJECT BACKGROUND
Arun Kabeli Power Limited is constructing 25 MW Kabeli B1 HEP in Kabeli River in the border of Taplejung and Panchthar districts. The construction of the project is in the full swing.

Salient Features of Kabeli B1 HEP
General

Development Region
Eastern
Zone
Mechi
Districts
Panchthar/Taplejung
Name of River
Kabeli
Nearest Town
Ganesh Chowk
Type of Scheme
Run of River
Gross Head
93.80m
Net Head
82.45m
Installed Capacity
25,000 kW
Annual Energy after outage
141.746 GWh
Hydrology

Catchment Area
710 km2
Design Discharge
36.14 m3/s
Riparian Release
0.983 m3/s
Design Flood Discharge
1,022 m3/s (100 yr. flood)
Annual Precipitation
2,508 mm
Diversion Weir

Type of Weir
Free flow concrete weir
Length of Weir
38 m
Crest Elevation
EL 703.40 m
Intake

Type
Side Intake
Size
5m x 4m
Nos.
4
Undersluice Structure

No of gates
2 nos, Radial Gates
Size
6m x 5m
Desanding Basin

Type
RCC Rectangular, Surface
No of bays
2
Dimension (LxBXH)
140m x 14m x 7.18m~10 m
Particle size to be settled
0.20 mm (90% trapping efficiency)
Headrace pond/forbay at desanding basin

Length
28.50m
Size
15.75m x 17.40m
Headrace pipe

Type
Welded Ribbed Pipe
Diameter
3.95m
Length
4,479m
Thickness
10 mm ~ 20 mm
No. of Anchor Blocks
40 nos including T and bell mouth block
No. of Manhole
1
No. of Y
from 3.954m dia to 3.75 m dia
Surge Tank Facilities

Type
Vertical Cylindrical Concrete Structure
Material
Concrete
Diameter/Height of Surge Tank
16.00 m/18.50 m
Full Supply Level
702.80 m
Connection Pipe to ST
Buried MS pipe of 4 m dia
Length of Connection pipe
200 m
Penstock Pipe

Type
Welded Ribbed Pipe, open/buried
Dia
3.75m~2.85m
Length
288m
Thickness
14 mm~32mm
Powerhouse

Type
Surface
Size
38.20m x 18m
Height
12.5m
Tailrace

Type
Rectangular, Close Duct
Length
47.10m
Size
6.31m x 4m
Turbine

Type
Vertical Axis Francis
No. of units
2
Efficiency
91.50%
Generator

Type
Synchronous 3 phase
Rated Output Capacity per unit
16000 KVA
Power Factor
0.8
Voltage
6.3 kV
Frequency
50 Hz
No. of units
2
Efficiency
96.50%
Transformer

Type
Three phase, oil immersed outdoor
No. of Units
2
Vector Group
YND 11
Rated Capacity per Unit
16200 KVA
Voltage ratio
132 kV/6.3 kV
Efficiency
99%
Transmission Line

Voltage Level
132 kV, Single Circuit
Length
4.5 Km
From
Powerhouse
To
Amarapur Substation


a. Project status
 
Headrace pipe
2,000 m completed
Intake
50% completed
Desander
50% completed
River training
100% completed
Powerhouse
Foundation completed
Electro-mechanical
Mobilization advance paid by opening L/C
Transmission line
Land required for the construction of 4.5 km (17 towers) transmission line from Powerhouse to Amarpur Substation has been purchased. Also the Tower foundation parts have arrived at the project site.
Targeted COD
By the end of Ashad 2074
Source:- IPO Prospectus




b. Project cost
The total completion cost was estimated at NPR. 4 billion at the time of financial closure where debt equity ratio was 70:30. Consortium banks agreed to finance 70 percent or NPR 2.8 billion and the rest NPR 1.20 billion was supposed to be the equity investment. However, the developers raised the equity to NPR 1.5 billion from NPR 1.2 billion at the time of IPO issuance to mitigate the likely cost overruns during construction.

This makes the total estimated project cost at NPR. 4.3 billion that translates to per MW cost of NPR 172 million.

c. Machinery
Electro-mechanical equipment is supplied by Andritz Hydro, Austria. It is a renowned company in the field of electro-mechanical equipment. Reliability and efficiency will be ensured.

The price of electro-mechanical equipment is US$ 6,750,000 (US$ 270 per kW)

d. Contract energy
The total contract energy is 141,746,470 kWh. This makes Plant Load Factor (PLF) of 64.72 percentage. This is considered as a good project in terms of energy generation.

e. PPA rates.
The Power Purchase Agreement (PPA) was completed on Ashad 29, 2069 B.S. The applicable PPA rates are 8.40 per kWh during dry season (4 months) and NPR. 8.40 per kWh during wet season (8 months). The Company is entitled to get five escalations from the date of commercial operation at 3 percent (simple growth).

f. Transmission line
The power will be evacuated by constructing a 4.5 km 132 kV single circuit transmission line from the power house to Amarpur substation which lies in the World Bank funded project “Mechi corridor transmission line project”.

Transmission line from Damak to Godak substation has been completed. However, from Godak substation to Thapatar substation (41 Km) and from Thapatar substation to Amarpur substation (13 km) are still under construction.

In order to speed up the construction of transmission line, the developers of the project (Arun Kabeli Power Limited) is leading/constructing the 13 km Thapatar-Amarpur substation (40 towers). Till now, 14 towers have been completed and now the developers are planning to complete this 13 km section by the end of Poush 2073.

The Thapatar-Godak 41 km section is the critical section which is also under construction. It is constructed by Jaguar-Aster JV. Erection of towers in Phidim is the most problematic area of this section.

2) SHARE CAPITAL
Authorized capital is NPR 1,500,000,000 while the issued capital is NPR. 1,500,000,000. The detail breakdown of the issued capital is presented in the table below.

Details
Amount (NPR)
Percentage
Promoter
1,050,000,000 
70%
Local
     150,000,000
10%
General Public
     300,000,000
20%
Total Issued Capital
1,500,000,000
100%
 
3) MANAGEMENT TEAM
Mr. Guru Prasad Neupane, chairperson, leads the Company. He is a well known figure in Nepali hydro. Mr. Guru Prasad Neupane and his team have already constructed several hydropower projects in Nepal.

4) KEY FINANCIAL HIGHLIGHTS

Actual
Fiscal Year
2070/71
2071/72
2072/73
Share Capital (000)
420,530
745,632
1,200,000
Reserves and surplus (000)
-8,236
-5,704
-11,080
Long term debt (000)
 -
868,001 
Short term loan (000)
-
-
170,000
Revenue from electricity sale (000)
 -
Other Income (000)
1,177
15,295
1,217
Administrative Expenses (000)
3,223
9,390
2,619
Advance to others (000)
89,021
250,381
379,249
Profit/loss (000)
-3,938
2,532
-5,376 
Net Worth
98.04
99.24
99.08
EPS
-0.94
0.34
-0.45
* Source : IPO Prospectus.

The Company has been earning interest income in the past three years.


Projected

Fiscal Year
2073/74
2074/75
2075/76

Share Capital (000)
1,500,000 
1,500,000
1,500,000

Reserves and surplus (000)
-19,885
287,989
658,596

Long term debt (000)
 2,800,000
2,664,107 
2,515,466 

Short term loan (000)
220,007
33,923
54,397

Revenue from electricity sale (000)
 -
762,774 
785,658 

Other income (000)
450
23,195
36,420

Administrative Expenses (000)
3,873
21,124
22,173

Operation Expenses
-
28,788
30,797

Royalty
-
17,755
18,213

Interest Expenses
-
264,485
235,537

Profit/loss (000)
-8,805
307,874
370,604 

Net Worth
98.67
119.20
143.91

EPS
-0.59
20.52
24.71

* Source : IPO Prospectus.


 The financial projection of the company seems to be attractive. However, the projection is based on the assumptions that the project will come into operation by the end of Ashad 2074, 9% interest rate and supply of total contracted energy to NEA.

5)IPO
The Company is floating 20% of its issued capital to the general public after issuing 10% of its issued capital to the local people few months back. Siddhartha Capital Limited is the issue manager. The amount collected from the IPO will be utilized in construction of the project itself

6) ICRA RATING
ICRA Nepal Limited (ICRA Nepal), the first Credit Rating Agency in Nepal, is a subsidiary of ICRA Limited (ICRA) of India.

ICRA Nepal has assigned "IPO Grade 4+", indicating below average fundamental, to the proposed initial public offering (IPO) of Arun Kabeli Power Limited. ICRA Nepal assigns IPO grading on a scale of IPO Grade 1 through IPO Grade 5, with Grade 1 indicating strong fundamentals and Grade 5 indicating poor fundamentals. For the grading categories, 2,3 and 4, the sign of + (plus) appended to the grading symbols indicate their relative better position within the grading categories concerned.

7) MY VIEWS

i) RCOD of the project is on Baishak 10, 2074 while the company is planning to commission the project by the end of Ashad 2074. This to me is very unlikely. Timely construction of transmission line will be the key factor.

Having said that, I am pretty sure the Company will get the extension of RCOD since Mechi Corridor transmission line is not completed which is in the scope of NEA.

ii) The financial projection is made on the assumption that the project will supply total contracted energy. Unfortunately, I have not seen any project supplying total contracted energy in recent times. So I take the developers' claim with a grain of salt.

iii) The Company has raised the issued capital to NPR 1.5 billion from NPR 1.2 billion. More share capital means more hungry mouths to feed throughout life.

iv) The price of electro-mechanical equipment is US$ 270 per kilowatt. It is on the higher side.

v) The contract for hydro-mechanical and civil works have been awarded to Api Hydro-mechanical Company and Palanchwok Construction Company respectively. These companies are affiliated to Mr. Guru Prasad Neupane. Conflict of interest may arise in such case. However, smooth and efficient construction is possible when in-house companies are involved. Unlike other projects, disputes between the contractors and the developers are not likely to occur.

vi) The estimated per MW cost of NPR 172 million even with the NPR. 1.5 billion equity is in the lower side compared to the per MW cost of recently completed projects. Having said that, time will tell the actual cost per MW.

vii) It is safe to say that the project will come into operation by the end of Chaitra, 2074 (in my opinion)

viii) Regarding the dividend, let’s do a realistic calculation. First, deduct 10 percent from the forecasted revenue since no hydropower company is delivering the designed Plant Factor. This makes the first year income of NPR. 686 million ( NPR. 762 million x 90%). Out of this amount, NPR. 402 million approx. has to be allocated for the interest and principal payment (assuming 10 percent interest rate with 12 years of repayment schedule). This leaves to NPR. 284 million. From this amount, NPR 72 million is deducted (Administrative expenses, operation expenses and royalty). So the net saving will be roughly NPR. 212 million. Now do your own calculation for the dividend purpose.

Finally 
After the overwhelming response shown by investors in recent hydropower IPOs, I am pretty sure this one will be oversubscribed too. As for the share price when listed in NEPSE, I will leave it up to you to speculate. I know you are experts.

2 comments:

  1. Thank you for sharing, the information is very useful. If you are in the water system can visit my site offline. thank you........


    van điều khiển khí nén

    van điện từ

    Van điện từ áp lực cao (D15 -D50)

    Van điện từ thường mở

    van công nghiệp

    ReplyDelete
  2. It has been great to know that there is someone out there that knows about falling down and getting back up. We always stay humble and never give up, and for the help of Mr Pedro in getting me Loan from his firm to expand my business, at a pivotal time. The support I received from his loan firm was quite honest and an interesting low rate in return, Mr Pedro Jerome is a loan officer working with a loan company which is willing to fund any type of business or give loans for personal use as long as their repayment is guaranteed.
    You can contact theirs email on pedroloanss@gmail.com Via WhatsApp:+1-863-231-0632

    ReplyDelete