Madhya Bhotekoshi Jalavidhyut Company Limited (MBJCL) is a
subsidiary company of Chilime, registered as public company in july 2010. MBJCL
has planned to develop Middle Bhotekoshi Hydroelectric Project (MBKHEP) with an
installed capacity of 102 MW in Sindhupalchowk district of Central Development
Region.
Tri-partite loan agreement has been signed between EPF, Chilime and MBJCL for debt portion. The equity investment will be made through 51% promoter share and 49% public share. Chilime is a leading company with 38% share.
Tri-partite loan agreement has been signed between EPF, Chilime and MBJCL for debt portion. The equity investment will be made through 51% promoter share and 49% public share. Chilime is a leading company with 38% share.
Project: Introduction
Type
of Project:
|
Run-of-River
(ROR)
|
Design
flow:
|
50.8
m3/sec
|
Gross
Head:
|
235
m
|
Headworks:
|
Gated
Weir Type with Undersluice and Side Intake
|
Desanding
Basin Type & Size:
|
Surface,
100 m(l) x 13 m(w) x 8.5 m(h)
|
Tunnel
Length & Size:
|
7124
m x 5.7 m(w) x 5.7 m(h)
|
Powerhouse
Type & Size:
|
Semi-underground,
52 m(l) x 15 m(b) x 25.5 m(h)
|
Turbine:
|
Type,
Orientation & Number
|
Unit
Capacity:
|
Francis,
Vertical Axis & 3 Nos. 36 MWdf
|
Generator
Unit Capacity & Nos.:
|
40
MVA & 3 Nos.
|
Installed
Capacity:
|
102
MW (3 x 34 MW)
|
Annual
Salable Energy:
|
542.2
GWh
|
Dry
Energy:
|
83.7
GWh
|
Wet
Energy:
|
458.5GWh
|
Transmission
Line Length/ Voltage:
|
4
km/220 kV
|
Status of Project
PPA has been signed with NEA on 14
th November 2011.
Financial closure has been
completed.
The project is scheduled to start
construction by January 2013 and targeted to complete the project by the end of
December 2016.
Request for Proposal for consulting
services from shortlisted firms have been submitted and evaluation is
completed.
Pre-qualification of construction
companies for Lot-1 (Civil and Hydromechanical works) EPC contract is
completed.
Consulting services is awarded to
Lahmeyer Internation GmbH(LI) in association with TMS.
Tender document preparation is in
progress.
Detailed Project Report has been
completed.
Hydrological measurements at
headworks and powerhouse site is being continued.Surface geological investigation
including drilling in headworks and powerhouse as well as sub-surface
exploration with ERT has been carried out to determine the geological condition
in the key structure locations.
EIA study of the project is in final
stage.
Land acquisition process is in
progress to acquire land required for the project.
Test Adit is constructed by Himal
Hydro Construction Ltd.
Camp Facilities are under
construction.
Diversion Tunnel is Constructed by
Himal Hydro Construction Ltd.
EIA approved 12 th November 2013
Generation License received 03
rd December 2013
Lot-1 (Civil and Hydromechanical
works) contract is awarded to Guangxi Hydroelectric Construction Bureau.
Lot2 (Electro-Mechanical Contract) is
Awarded to Andritz Hydro Private Limited in association with Trade Link
International.
No comments:
Post a Comment