The
company has aimed to develop Rasuwagadhi Hydroelectric Project having capacity
of 111 MW. It is located in Rasuwa district, Bagmati Zone of Central
Development Region. The project is accessible by the Kathmandu -Trisuli -
Somdang road at a distance of 130 km to the north of Kathmandu to reach to
Syabrubesi and then around 16 km from Syabrubesi to the project site at
Rasuwagadhi. A 50:50 debt-equity structure will be employed for financing this
project.
General Overview
The design discharge of the project is 80m3/sec in Q40 exceedance of time. The headworks site is located about 400 m downstream from the confluence of Kerung khola and Lende khola which are the Boundary Rivers of Nepal and China (Tibet). The total headrace tunnel length of the project is 4196 m up to the surge tank. Tail water from the powerhouse will be released to main river course through 598.55 m long tailrace tunnel in the downstream of powerhouse site. The Headwork site of the project is located on the Thuman and Timure VDC at Rasuwagadhi, whereas all other project components lie in Thuman VDC. The project is basically a run-of-river type scheme having the capacity of 111 MW and the annual energy generation is 613.875 GWh with the available gross head of 167.9 m.
Key Features of the Project
Location
|
Thuman & Timure V.D.C. of
Rasuwa district.
|
Type of Project
|
Run-of-River (ROR)
|
Design flow (Q40)
|
80.00 m3/s
|
Gross Head
|
167.90 m
|
Headworks
|
Overflow Diversion Weir with side
off intake
|
Tunnel length and size
|
4196.0 m x 6.0m (w) x 6.0 m (h):
Concrete lined finished
|
Powerhouse Type and Size
|
UGPH 76.30m x 15.0 m x 35.5 m
|
Turbine capacity and type
|
3 Nos., 38.50 MW each, Francis,
Vertical Axis turbine
|
Generator capacity and type
|
3 Nos., 43.75 MVA each, 3 Phase
Synchronous AC
|
Installed capacity
|
111 MW (3 x 38.5 MW)
|
Annual Energy Generation
|
613.875GWh
|
Dry Months Energy
|
84.318 GWh
|
Wet Months Energy
|
529.557 GWh
|
Transmission line length/ voltage
|
10.0 km / 132 kV (Double Circuit)
|
Share Structure
Chilime Hydropower
Company
|
33%
|
Nepal Electricity
Authority
|
18%
|
Project-affected Local
People
|
10%
|
Employees of the
Promoters
|
3.5%
|
Employees of EPF
|
1%
|
Depositors of EPF
|
19.5%
|
General Public
|
15%
|
Total
|
100%
|
PRESENT STATUS OF
THE PROJECT
PPA
has been signed with NEA on November 14, 2011.
Debt.
Portion of the project will be fully financed by EPF for which the tri-partite
loan agreement has been signed on 8 December, 2011 between RGHPCL, CHPCL and
EPF.
Selection
of the Consultant has been made and contract has been signed on 3rd December,
2012.
Pre-qualification
for the civil and hydro-mechanical works in EPC model to construct RGHEP has
been completed and Bid document has been issued to the pre-qualified bidders.
Surface
geological investigation, ERT works including drilling in headrace tunnel and
tailrace tunnel has been carried out to determine the geological condition in
the key structure locations.
Generation
license has been obtained from DoED on Dec 6, 2012.
Certificate
of Registration in Industry was obtained on July 3, 2012.
Grid
connection agreement with NEA has been completed.
The
Environmental Impact Assessment (EIA) report has been approved from the
Ministry of Environment.
Detail
survey of double circuit 132 kV transmission line has been completed and design
is under process.
Private
land acquisition has been completed.
125m
out of 260m test adit tunnel at powerhouse site has been constructed.
Construction
of 11 kV construction power line from Chilime hub to the project site has been
completed.
Contract
for the construction of Camp Facilities has been awarded and construction works
has been started.
IEE
for 10 km long Transmission Line is under progress.